Progress Update on Tunnel-4 Construction of NCPCP

Re-awakening sessions for government stakeholders on baseline data collection for CAD farmers engaged in commercial fruit crops were successfully completed.
During the two-day field visit, key meetings were held with the Department of Agriculture, Department of Agrarian Development, and Divisional Secretariats, alongside field visits including

Significant progress has been achieved in the construction of Tunnel-4 (T-4) under the North Central Province Canal Project. This tunnel section, approximately 1,100 meters in length, is being constructed using the New Austrian Tunnelling Method (NATM), a conventional drill-and-blast technique.

Tunnel-4 extends from the northern tunnel portal to the northern tunnel outlet, covering the section between Chainage Km 54+300 and Km 55+400, in close proximity to Namalpura Village within the Madawala GN Division of the Palugaswewa Divisional Secretariat.

This section plays a critical role in connecting with the 26.6 km tunnel stretch excavated using a Tunnel Boring Machine (TBM), which runs from the northern portal to the southern portal of the canal system.

Construction Progress –

The contractor has recently commenced invert concrete works within Tunnel-4. To date:

Invert concrete has been completed up to Section 32, covering a cumulative length of 346.783 meters.
Crown and wall concrete lining works have been completed up to Section 8 (excluding Section 7), reaching a total length of 83.2 meters.

The Employer has instructed the Engineer to closely monitor both progress and quality, ensuring that construction activities meet the required technical and safety standards.